The overhang to the next strip should be 3 8 inch.
Nail pattern for roofing felt.
The top edge of the felt should be nailed no less than every eight inches.
Pay careful attention to roll the felt out smoothly avoiding wrinkles as you move across the roof.
All nails and staples should be placed on the lower half of the paper.
It does not have to be perfect but you may need to realign the drip edge.
Contact roofhelp 12 24 nailing pattern for roofing felt each row of nails that are 24 on center should be approximately 12 from the outside edge of the roll.
Where a roll ends and a new one is begun the two rolls should be overlapped by four inches.
Snap a chalkline to help you align the wsu or felt.
Roof rafters to ridge valley 2 16d common end nail.
Roll out about 10 feet of felt and fasten with staples or roofing nails with plastic washer heads.
The paper should then be nailed in or stapled every three to four inches across.
The wsu should overhang the drip edge by 1 2 inch so snap a line that is 35 1 2 inches above the drip edge.
Check at several points to make sure the overhang is consistent.
Overhang is not required.
Anchor the top corner of the felt after it has been properly positioned and roll the felt out across the roof.
Put fasteners at least every 8 inches.